High availability and correct maintenance from the start-up CFB boiler
Aug 23, 2023
High availability and correct maintenance from the start-up of the CFB boiler at Sappi Kirkniemi pulp and paper mill in Finland.
Summary
Location
Sappi Kirkniemi, Finland
Customer challenge
The need for a systematic approach to evaluating the condition of the new plant so that optimized availability, risk management, and preventative maintenance can be achieved.
Solution
A service agreement with Valmet that includes:
Outage planning and supervision
Visual inspections during shutdowns
Boiler tube thickness measurements
Outage reporting
Upkeep of maintenance system (Valmet works)
24/7 On-call service
Result
By entering into a partnership directly at the commissioning of the facility plant, the availability has been high since the start, and the correct preventive maintenance services have been performed.
Technical summary - Valmet CFB boiler and Bag House Filters (BHF)
Start-up date
2015
Steam
88 MWth, 32 kg/s, 81 bar, 520 °C
Fuels
Bark, forest residue, fiber sludge, bio sludge, coal, asphaltene
Reason why we wanted a service agreement with Valmet, was to have a systematic approach for evaluating the condition of the new plant. High availability, risk management, and correct preventive maintenance based on all relevant data were the driving forces for us.”
Power Plant Manager, Sappi Kirkniemi