Customer case:

Stora Enso Ostrołęka, Poland

Jul 30, 2018

StoraEnsoPoland570x277.jpg

Summary

Location Stora Enso, Ostrołęka,
Poland
Solution

3-year Service Agreement for Valmet CFB Boiler

The agreement included:

Annual inspections of boiler and auxiliary equipment
  • Boiler pressure parts
  • Auxiliary equipment
Engineering services based on request:
  • Trimming, commissioning and maintenance services
  • Additional training
  • Analyzing CFB-process problems, etc.
Keywords Performance agreements, Pulping and fiber, Europe
   
   

Technical data

Plant
Combined heat and power plant (CHP)
Capacity Boiler 164MWth
Fuels Biomass, paper and fiber rejects, sludge, coal